The agency building the new World Trade Center is “dysfunctional” and has let costs get out of control on the $14.8 billion project, auditors said Tuesday.

The projected cost of the complex has risen $3.8 billion since 2008, when it was estimated at $11 billion, Navigant Consulting, Inc., said in its audit of the Port Authority of New York and New Jersey.